Ganir Bridge Replacement Project Advances Through Preparatory Works Amid Schedule Delays

7 hours ago
2 min read

Wednesday, November 18, 2026 /// DYCA PIO


Yap FM - The Ganir Bridge Replacement Project continues to progress through key construction preparation activities, with geotechnical investigations underway and coordination ongoing for the temporary relocation of Vital's fuel pipeline before major foundation works can begin.


According to the latest project update dated November 12, 2026, submitted by SMEC Senior Resident Engineer Mr. Ichael Paice, the project has completed demolition of the former bridge deck and steel girders, along with the construction of drilling platforms in preparation for the new bridge foundations.


Geotechnical investigations commenced on November 9, 2026, and will involve four planned boreholes to determine ground conditions and establish the technical requirements for the new bridge foundations. The findings must be completed and reviewed before critical piling works can proceed.


Meanwhile, the temporary relocation of Vital's existing fuel pipeline remains one of the project's major outstanding priorities. SMEC, the contractor Shandong Hengyue Municipal Engineering (SHME), and Vital continue coordinating the proposed temporary pipeline route, technical approvals, and necessary safety arrangements. Updated utility layout plans are also being prepared for review by the Yap State Public Service Corporation (YSPSC) and Vital to address existing water, electricity, sewerage, and other services within the bridge construction area.


A significant development in the utility coordination process was the temporary sewer diversion, which became operational on October 3, 2026, removing an important obstacle to the demolition process. However, further technical reviews and approvals are still required before the remaining utility-related construction activities can proceed.


Despite these developments, the project remains substantially behind schedule. Under the current contract, the project is scheduled for completion on November 29, 2026, following a 60-day interim extension granted in September. However, SHME's revised construction programme, submitted on November 10, forecasts completion by October 31, 2027. This proposed timeline remains subject to the Engineer's assessment and has not been formally approved as an extension of the contractual completion date.


In a memorandum to the Governor, the Director of the Office of Planning and Budget (OPB) highlighted the temporary relocation of the Vital fuel pipeline and completion of the geotechnical study as the immediate priorities before critical piling works can begin. The memorandum accompanied the project update submitted by SMEC's Senior Resident Engineer for the Governor's review.


Other completed activities include the replacement of the project's silt curtains, with no current safety or environmental issues reported in the latest update. The Engineer will continue monitoring construction progress, safety measures, and coordination among the contractor and utility providers.


The Department of Transportation, Communications and Infrastructure (DTCI) will continue facilitating coordination with utility providers and addressing matters requiring government involvement. Meanwhile, the contractor remains responsible for its construction methods, workforce, safety arrangements, and delivery of the remaining project works.


The Ganir Bridge Replacement Project remains an important infrastructure undertaking for Yap. Completion of the outstanding geotechnical investigation, resolution of the fuel pipeline relocation, and timely coordination of utility requirements will be essential to advancing the major construction phase and moving the project toward completion.


(For more information, please contact the Department of Youth and Civic Affairs at 350-DYCA)



Comments


Yap State Government 

About Us:

The State of Yap is one of the four states that make up the Federated States of Micronesia, along with the states of Pohnpei, Chuuk and Kosrae. Yap is the Western-most island in the FSM, located about midway between Guam and Palau.

Executive Branch

Legislative Branch

Judiciary Branch

Traditional Leaders

IMG-0078.jpg
IMG_0501.jpg
court.webp
3620701832_124a4b9321_b_edited_edited.jp

Department of Youth and Civic Affairs
Website Office
(691) 350-DYCA

Email: website.dyca@gmail.com
P.O.Box 430
Colonia, Yap State, FM, 96943

 

  • Instagram
  • Facebook
  • LinkedIn
bottom of page